This project was supported by the National Science Foundation (NSF) under Grant Number 1640228. Any opinions, findings, conclusions, or recommendations expressed in this project are those of the author(s) and do not necessarily reflect the views of the National Science Foundation. If you have any questions, please contact Dr. Dazhi Yang at dazhiyang@boisestate.edu or use our Contact Form.

Description

This project-based scientific inquiry project: Earthquake and Boise River Bridge Design is centered on researching different types of bridges, various aspects of earthquakes, and seismic safety features of bridges. In this project, students work in small groups to explore different bridge types, the destructive aspects of an earthquake, and the safety features for bridges that could resist earthquakes. Then students will design an earthquake-tolerant bridge and test their design with an earthquake simulator. To develop computational thinking and an understanding of STEM subjects, students from 4th, 5th and 6th grade will work in small groups of six, with one in-service teacher and one pre-service teacher, twice a week for eight weeks in a community centers after-school program.

Implementation

Please refer to the weekly activities (such as Week 1 Session 1 in the left sidebar and Resources from the sections below) for detailed information on how to use this project either in a classroom or an informal setting such as in community centers' after-school programs. The twice weekly sessions were originally designed to be 90 minutes in length, including a 10 minute break in the middle of the session. See photos of prior implementations on the projects' photo pages.


Week 1


Session 1
Questions

What is the goal of this project?

What is a bridge and how does a bridge work?

space


Goal

To understand the project

To understand the bridges in society


Activities

Watch videos on bridges

Research about bridges

space


Resources

Bridge Facts

How bridges work

Videos


Outcomes

Journal Keeping

Project Goal

Presentation on bridge functions

Session 2
Questions

What are the different types of bridges? (focuses on four types bridges)

When would a bridge designer want to use each type of bridge?


Goal

To research about different types of bridges

To understand the different parts of a bridge


Activities

Research about different types of bridges

Some hands on building activities

Learn about EV3 robot parts


Resources

Directions for each station

Video

space


Outcomes

Journal Keeping

Project Goal

Presentation on bridge functions

How can we build a bridge for the Boise River that is strong enough to resist earthquake forces?


Intro 10-15 minutes

1. A teacher/lead explains the overall Bridge project.

What is the Bridge project about? Groups learn about earthquakes and how to design a strong and earthquake resistant bridge for the Boise River in Boise, ID.

Why? Because Idaho has several active earthquake zones.

How long is the project? Twice a week for eight weeks.

Who are you going to work with? In a small group of six peers and one teacher and one college student who is likely to become teacher in the future!

What is expected from you? You will work on a 8-week project with your peers and your teachers; you'll need to pull all your knowledge about earthquakes, bridges, and bridge design together with your math skills and more to build a bridge to compete with another two groups of students for the best bridge design at the end of the program!

There will a prize for the winning team.

Let's look at some pictures from the previous competition!


Image of Bridge Judging

Bridge Judging

Judges are examining the final bridge designs.

Image of Bridge Testing

Bridge Testing

Judges are testing out their bridge designs.

Image of Bridge Testing

Bridge Testing

Dr. Chittoori tests out one of the group's bridge.

Image of Bridge Testing

Bridge Testing

Dr. Chittoori and an after-school center teacher test out a group's bridge.

Image of the winning bridge Spring 2017

The Winning Bridge

The STEM+C Team and Facilitation Teachers with the winning Spring 2017 bridge.

Image of the winning team Spring 2017

The Winning Team

The winning team and their bridge from Spring 2017.



2. Team building Activity: Before we start to work together as bridge engineers, we need to get to know each other! Let's introduce ourselves by starting with your name, your grade, your school and why you want to come to this program! (Provide students with a piece of paper to write down their own information and then each student introduces him/herself.) 10 minutes

3. After the introduction to the project and the self introduction, a teacher asks, "Why do we need bridges? Imagine a world with no bridges? How would life be different for us? What do you know about bridges? What are some types of bridges you noticed when traveling? How do you think bridges are built?" A teacher summarizes the conversations by introducing the Biggest question we want to answer in the following 8 weeks that is: How can we build a bridge for the Boise River that is strong enough to resist earthquake forces? 5 minutes


Problem Solving Process 5 minutes

Here is a good time to introduce the Problem Solving Process to students. Briefly explains the diagram and let the students know that they will refer to this diagram frequently to guide them in problem solving and reflecting upon what they have done later on.

Problem Solving Process Diagram
What is a bridge and why do we need it? Small-group Hands-on Scientific Inquiry 25 minutes

A teacher asks “What do you notice about bridges in Boise? Do you see different kinds of bridges, or do they all look the same?” PAUSEs for responses. "Let's look at a very famous bridge!" Golden Gate Bridge in San Francisco. PAUSEs and asks “What are some questions you might have about bridges, perhaps like this one, and why do we use them?”

After the watching the video, a teacher asks “Why do various bridges look different from each other?” PAUSEs, allows the learners to share their ideas and offer suggestions. “What should a bridge be made out of and why?” PAUSEs for responses and compares learner opinions. “What do you think is the best kind of bridge?” Teacher shows the students that there are four major bridge types, which may be remembered using the acronym “ABCS”:

Arch

Beam

Cable

Suspension

The teacher shows images of each type of bridge as they are named. Teacher explains that each of these bridge designs work differently. Students have the opportunity to explore each of the four bridge types and how they work. Students take note of the similarities and differences of the bridge types. In their groups, the learners are responsible for presenting their journal observations of one bridge type, as assigned by the teacher.

The teacher explains that bridge design and construction is a very important STEM topic, and that the students will be exploring the topic of bridges to learn more about the considerations in bridge engineering. To start their investigations, the learners are guided to work in teams to gain more knowledge about the different purposes, styles, and science of bridges in an open-ended inquiry task. The students will record their findings and will be asked to reflect on their research and share the most important facts learned with the whole class.

Here are questions students will research and seek answers to using the resources provided:

1. What is a bridge?

2. Why do we need bridges?


Resources

What is a bridge and some facts of bridges

What is a bridge and the function of a bridge? (Please pay attention to the highlighted words for correct terminology for bridges.)

Bridges and Forces 1: The Basics (This helps you understand how a bridge works! Please pay attention to the highlighted text.)

Interesting Bridge Facts 1

How Bridges Work

The following diagrams show the different parts of a bridge. As a bridge engineer, you'll need to name the parts correctly!

Image of a bridge and terms of its parts
Image of a bridge and terms of its parts
Presentations 10-15 minutes

The teacher asks the students to present their research findings on what a bridge is and the functions of a bridge (Either individual oral or group presentation). All students’ ideas should be discussed by the whole group.


End of Session Reflection and Debriefing 5-10 minutes

Teacher briefly explains the computational thinking (CT) skill embedded in the Problem Solving Process Diagram. Using the problem solving process diagram, the teacher will ask students to identify what kind of problem solving skills/process/computational thinking they used in this session and explain how they used it. The following are some sample questions that can guide the debrief.

What did I learn today?

What problem solving skills/processes or CT components in this diagram did I use today?

How did I use the problem solving skills/processes/CT components?

How can we build a bridge for the Boise River that is strong enough to resist earthquake forces?


Bridge-Type Rotation Stations Small-group Hands-on Scientific Inquiry 60 minutes

Let's do this activity in groups. There are 4 stations/simulations in this activity – one for each of the four bridge types. Each station/simulation will spend approximately 15 minutes to simulate how different types of bridges function. Each student should participate in all four simulations, and must record detailed observations in their notebooks – how does each type of bridge work, and what is the best use for that bridge type? What are some risks or benefits of that type of construction?

The teacher is the timekeeper, monitoring student efforts and alerting when it is approaching time for station rotations. The teacher needs to guide students to think about how to record their observations after each simulation and after the first two rotations have been completed. approximately 30 minutes

The directions for each station are provided below. The teacher prints the directions and includes them at each station for the students to use. There should be four stations for each bridge-type.

Each station should be tested before the session by the teacher to determine appropriateness for students. The Cable Station, in particular, requires careful, considerate student interaction.


Arch Bridge Station Simulation: How Do the Abutments Support an Arch Bridge?

Resources needed - at least 4 pieces of cardboard, cut into 1” x 11” strips (Please prepare the materials ahead of time).

Bixby Creek Bridge, Monterey, CA Photo credit: © Jay Spooner/iStockphoto

Bixby Creek Bridge, Monterey, CA Photo credit: © Jay Spooner/iStockphoto

Instructions - Cut a strip of cardboard that's about one inch by 11 inches. Gently bend the strip so that it has a curve.

Step 1: Position the cardboard on a table so that it resembles an arch. Press down on the center of the arch. What happens to the ends of the cardboard?

Step 1

Step 1

Step 2: Next, place a stack of books at each end of the arch. Press again. Now what happens? Notice how the stacks of books act as abutments, keeping the ends of the arch from spreading outward.

Step 2

Step 2


More Background Information

This is more for the teachers and facilitators to acquire more background knowledge of each type of bridges in order to facilitate this session.

Arch bridges are one of the oldest types of bridges. Arch bridges have great natural strength. Instead of pushing straight down, the weight of an arch bridge is carried outward along the curve of the arch to the supports at each end. These supports, called the abutments, carry the load and keep the ends of the bridge from spreading outward.

When supporting its own weight and the weight of crossing traffic, every part of the arch is under compression. For this reason, arch bridges must be made of materials that are strong under compression.

The Pont du Gard aqueduct Photo credit: © Agnieszka Gaul/iStockphoto

The Pont du Gard aqueduct Photo credit: © Agnieszka Gaul/iStockphoto

he New River Gorge Bridge Photo credit: © John Brueske/iStockphoto

The New River Gorge Bridge Photo credit: © John Brueske/iStockphoto

Today, materials like steel and prestressed concrete have made it possible to build longer and more elegant arches, including a spectacular 1,700-foot span in New River Gorge, West Virginia. (More typically, modern arch bridges span between 200 and 800 feet.)

One of the most revolutionary arch bridges in recent years is the Natchez Trace Parkway Bridge in Franklin, Tennessee, which was opened to traffic in 1994. It's the first American arch bridge to be constructed from segments of precast concrete, a highly economical material. Two graceful arches support the roadway above. Usually arch bridges employ vertical supports called spandrels to distribute the weight of the roadway to the arch below, but the Natchez Trace Parkway Bridge was designed without spandrels to create a more open and aesthetically pleasing appearance. As a result, most of the live load is resting on the crowns of the two arches, which have been slightly flattened to better carry it. Already the winner of many awards, the bridge is expected to influence bridge design for years to come.




Beam Bridge Station Simulation: What Happens when A Load Pushes Down on A Beam Bridge?

Resources needed - at least 3 sponges with notches cut into the top (see resource section).

Beam bridge Photo credit: © Andrea Pelletier/iStockphoto

Beam bridge Photo credit: © Andrea Pelletier/iStockphoto

Instructions - Take a small sponge and slice a shallow notch across the top and bottom. Create a beam bridge by supporting each end of the sponge with a stack of books. Press down on the center of the bridge. What happens to the top and bottom notches? Notice how the top notch squeezes together in compression, while the bottom notch spreads apart under tension.

Compression and Tension

Compression and Tension


More Background Information

This is more for the teachers and facilitators to acquire more background knowledge of each type of bridges in order to facilitate this session.

A beam or "girder" bridge is the simplest and most inexpensive kind of bridge. According to Craig Finley of Finley/McNary Engineering, "they're basically the vanillas of the bridge world."

In its most basic form, a beam bridge consists of a horizontal beam that is supported at each end by piers. The weight of the beam pushes straight down on the piers.

Prestressed concrete is an ideal material for beam bridge construction. The concrete withstands the forces of compression well, and the steel rods embedded within resist the forces of tension. Prestressed concrete also tends to be one of the least expensive materials in construction.

But even the best materials can't compensate for the beam bridge's biggest limitation: its length. The farther apart its supports, the weaker a beam bridge gets. As a result, individual beam-bridge girders rarely stretch more than 250 feet. This doesn't mean beam bridges aren't used to cross great distances; it only means that they must be daisy-chained together, creating what's known in the bridge world as a continuous span.

The Lake Pontchartrain Causeway, Louisiana Photo credit: © Gary Fowler/iStockphoto

The Lake Pontchartrain Causeway, Louisiana Photo credit: © Gary Fowler/iStockphoto

In fact, the world's longest bridge is a continuous-span beam bridge. Almost 24 miles long, the Lake Pontchartrain Causeway consists of a pair of two-lane sections that run parallel to each other. The Southbound Lane, completed in 1956, comprises 2,243 separate spans, while the Northbound Lane, completed in 1969, includes 1,500 longer spans. Seven crossover lanes connect the two main sections and function as pull-over bays in emergencies. Although impressive, the Lake Pontchartrain Causeway bridge underscores the drawback of continuous spans—they are not well suited for locations that require unobstructed clearance below.




Cable Bridge Station Simulation: How Do Cable-stays Work?

Resources needed - at least 3 strands of rope/string, each about 5’ long (length may be affected by student size) at least 3 strands of rope/string, each about 6’ long (length may be affected by student size)

William H. Natcher Bridge, Rockport, IN Photo credit: © David Sailors/CORBIS

William H. Natcher Bridge, Rockport, IN Photo credit: © David Sailors/CORBIS

Instructions - Stand up and hold your arms out horizontally at each side as showing in the picture below. Imagine that your arms are a bridge, and your head is a tower in the middle. In this position, your muscles are holding up your arms. Try making cable-stayeds to support your arms.

Rope Cable Stays

Rope Cable Stays

Step 1: Take a piece of rope (about five feet long), and have a partner tie each end of the rope to each of your elbows. Then lay the middle of the rope on top of your head. The rope acts as a cable-stayed and holds your elbows up.

Step 2: Have your partner tie a second piece of rope (about six feet long) to each wrist. Lay the second rope over your head. You now have two cable-stayeds. Where do you feel a pushing force, or compression? Notice how the cable-stays transfer the load of the bridge (your arms) to the tower (your head).


More Background Information

This is more for the teachers and facilitators to acquire more background knowledge of each type of bridges in order to facilitate this session.

Cable-stayed bridges may look similar to suspension bridges—both have roadways that hang from cables, and both have towers. But the two bridges support the load of the roadway in very different ways. The difference lies in how the cables connect to the towers. In suspension bridges, the cables ride freely across the towers, transmitting the load to the anchorages at either end. In cable-stayed bridges, the cables are attached to the towers, which alone bear the load.

The Sunshine Skyway Bridge Photo credit: © Tinik/iStockphoto

The Sunshine Skyway Bridge Photo credit: © Tinik/iStockphoto

The cables can be attached to the roadway in either of two main ways. In a radial pattern, cables extend from several points on the road to a single point at the top of the tower. In a parallel pattern, cables are attached at different heights along the tower, running parallel to one another.

Even though cable-stayed bridges look futuristic, the idea for them goes back a long way. The first known sketch of a cable-stayed bridge appears in a book called Machinae Novae published in 1595, but it wasn't until this century that engineers began to use them. In post-World War II Europe, where steel was scarce, the design was perfect for rebuilding bombed-out bridges that still had standing foundations. Cable-stayed bridges have gone up in the United States only recently, but the response has been passionate.

For medium-length spans—those between 500 and 2,800 feet—cable-stayeds are fast becoming the bridge of choice. And even longer cable-stayeds are going up, though suspension bridges are still used for the very longest spans. Compared to suspension bridges, cable-stayeds require less cable, can be constructed out of identical precast concrete sections, and are faster to build. The result is a cost-effective bridge that is undeniably beautiful.

In 1988, the Sunshine Skyway bridge in Tampa, Florida won the prestigious Presidential Design Award from the National Endowment for the Arts. Painted yellow to contrast with its marine surroundings, the Sunshine Skyway is one of the first cable-stayed bridges to attach cables to the center of its roadway as opposed to the outer edges, allowing commuters an unobstructed view of the magnificent bay. Recently, in Boston, Massachusetts, a cable-stayed design was selected for a new bridge across the Charles River—even though cheaper options were proposed. City officials simply liked the way it looked.




Suspension Bridge Station Simulation: What are the anchorages for?

Resources needed - 6 strands of string, each at least 3’ long, and perhaps longer

Golden Gate Bridge

Golden Gate Bridge

Instructions - Tie two loops of string around the tops of two hardcover books of similar size. Tie a third piece of string to each loop so that it hangs loosely between the books. Press down on the center string. What happens?

Rope Cable Stays

Suspension

Next, stand two books upright about 10 inches apart. Put a stack of heavy books on one end of a string to secure it to the table. Then pass the string over each standing book (letting some string hang loosely between the books). Place a second stack of books on the other end of the string. Press again on the center of the string. What happens? Notice how the anchorages (stacks of books) help to stabilize the bridge.


More Background Information

This is more for the teachers and facilitators to acquire more background knowledge of each type of bridges in order to facilitate this session.

Suspension bridges are pleasing to look at, light, and strong, and can span distances from 2,000 to 7,000 feet—far longer than any other kind of bridge. They also tend to be the most expensive to build. True to its name, a suspension bridge suspends the roadway from huge main cables, which extend from one end of the bridge to the other. These cables rest atop high towers and are secured at each end by anchorages.

The towers enable engineers to stretch the main cables over long distances. The cables carry most of the bridge’s weight to the anchorages, which are embedded in either solid rock or massive concrete blocks. Inside the anchorages, the cables are spread over a large area to evenly distribute the load and to prevent the cables from breaking free.

The Humber Bridge Photo credit: © Paul Hutchings/iStockphoto

The Humber Bridge Photo credit: © Paul Hutchings/iStockphoto

Some of the earliest suspension-bridge cables were made from twisted grass. In the early 19th century, engineers began using iron chains for such cables. Today, the cables are made of thousands of individual steel wires bound tightly together. Steel, which is very strong under tension, is an ideal material for cables; a single steel wire only 0.1-inch thick can support over half a ton without breaking. Currently, the Humber Bridge in England has the world's longest center span—measuring 4,624 feet.

Akashi Kaikyo Bridge  Photo credit: © GYRO PHOTOGRAPHY / amanaimages / Corbis

Akashi Kaikyo Bridge Photo credit: © GYRO PHOTOGRAPHY / amanaimages / Corbis

But this record won't stand for long. In 1998, the Japanese will unveil the $7.6 billion Akashi Kaikyo Bridge, linking the islands of Honshu and Shikoku via Awaji Island. The bridge's center section stretches a staggering 6,527 feet. To keep the structure stable, engineers have added pendulum-like devices on the towers to keep them from swaying and a stabilizing fin beneath the center deck to resist typhoon-strength winds.

Because suspension bridges are light and flexible, wind is always a serious concern—as the residents of Tacoma, Washington can surely attest. At the time it opened for traffic in 1940, the Tacoma Narrows Bridge was the third-longest suspension bridge in the world. It was promptly nicknamed "Galloping Gertie," due to its behavior in wind. Not only did the deck sway sideways, but vertical undulations also appeared in quite moderate winds. Drivers reported that cars ahead of them would completely disappear and reappear from view several times as they crossed the bridge.

Attempts were made to stabilize the structure with cables and hydraulic buffers, but they were unsuccessful. On November 7, 1940, only four months after it opened, the Tacoma Narrows Bridge collapsed in a wind of 42 mph—even though engineers had ostensibly designed the structure to withstand winds of up to 120 mph.

The failure came as a severe shock to the engineering community. Why did a great span, more than half a mile in length and weighing tens of thousands of tons, spring to life in a relatively light wind? And how did slow, steady, and comparatively harmless motions suddenly transmogrify into a catastrophic force?

To answer these questions, engineers began applying the science of aerodynamics to bridge design. Technical experts still disagree on the exact cause of the bridge's destruction, but most agree the collapse had something to do with a complex phenomenon called resonance, the same force that can cause a soprano's voice to shatter a glass.

Photo credit: © Lawrence Freytag/iStockphoto

Photo credit: © Lawrence Freytag/iStockphoto

This Tacoma Narrows Bridge opened in 1950, replacing the collapsed "Galloping Gertie." An even newer bridge now stands beside this one.

Today, wind-tunnel testing of bridge designs is mandatory. As for the Tacoma Narrows Bridge, reconstruction began in 1949. The new bridge is wider, has deep, stiffening trusses under the roadway, and even sports a slender gap down the middle—all to dampen the effect of the wind.


Facilitation Suggestions

At each station: at least 10 books (phone books are great) of similar size.

For each of the following resources, having a variety of sizes and lengths will improve the variety of student experimentation. Teachers should use discretion and test each station to determine the optimal size and effort for students.

At each of the four stations, the teacher needs to take the opportunity to facilitate student learning so that the station activities/simulations are both hands-on and mind-on activities. Some questions the teacher can ask are:

1. How does this type of bridge work?

2. Why would an engineer choose to create this type of bridge?

The Cooperative Learning and Teamwork Rubric is a tool for teachers to use to guide team work.


Resources

Directions for each station from NOVA/PBS

Cooperative Learning and Teamwork Rubric


Presentations 10 minutes

After completing each of the four stations, the teacher determines which stations will be presented by which groups. One method of selection is by student choice or request; another method is to have group present on the bridge station they visited last. Regardless of the motivation for selection, each student will seek to answer these three questions, as a group:

1. How does this type of bridge work?

2. Why would an engineer choose to create this type of bridge?

3. What are some famous bridges of this style that exist in the world?

After a few minutes of preparation, each student will speak to the group. Other students may offer their observations or questions after each students' presentation.


End of Session Reflection and Debriefing 5-10 minutes

Teacher briefly explains the computational thinking (CT) skill embedded in the Problem Solving Process Diagram. Using the problem solving process diagram, the teacher will ask students to identify what kind of problem solving skills/process/computational thinking they used in this session and explain how they used it. The following are some sample questions that can guide the debrief.

What did I learn today?

What problem solving skills/processes or CT components in this diagram did I use today?

How did I use the problem solving skills/processes/CT components?

Session 2

Directions for each station

Cooperative Learning Rubric

Problem Solving Process Diagram

Supplies Needed at Each Station:

8 books of similar size, 32 total

For each of the following resources, having a variety of sizes and lengths will improve the variety of student experimentation. Teachers should use discretion and test each station to determine the optimal size and effort for students.

Arch station: at least 4 pieces of cardboard, cut into 1” x 11” strips

Beam station: at least 4 erasers or sponges with notches cut into the top (see resource website/appendix)

Cable station: at least 4 strands of rope/string, each about 5’ long (length may be affected by student size) and at least 4 strands of rope/string, each about 6’ long (length may be affected by student size)

Suspension station: at least 12 strands of string, each at least 3’ long, and perhaps longer